Data center operators might pay $55 billion under Senate bill


A proposed Senate bill could generate $55 billion in transmission charges from data centers over 10 years if it becomes law. It would require large computing facilities to pay more for access to the electricity grid and the infrastructure needed to serve them.

For data center developers, the proposal could raise the cost of grid-connected projects, influence where new campuses are built and change the economics of behind-the-meter generation. It could also make firm transmission service more expensive relative to arrangements in which operators accept power curtailments during grid stress. Developers could face greater pressure to demonstrate load flexibility.

But shifting more costs to data centers addresses only part of the ratepayer problem. Utilities also need assurance that the large loads driving infrastructure investments will materialize, arrive on schedule and consume the electricity developers have promised.

The Bipartisan American Affordability and Jobs Act would require the Federal Energy Regulatory Commission (FERC) to revise its transmission-pricing policy. Under the proposal, utilities would charge data centers for both their share of existing transmission infrastructure and incremental costs associated with serving their loads.

Grid Strategies, a consulting firm that specializes in the power sector, estimated in a recently published white paper that the pricing changes would generate approximately $5.5 billion annually in transmission charges, compared with roughly $2 billion that data centers currently pay. The analysis projected a $35 billion increase over current arrangements across the decade.

The projected $55 billion includes $35 billion in embedded transmission costs and $20 billion in incremental costs. Both categories support the grid, but the additional revenue could enable transmission construction that otherwise might not happen, said Rob Gramlich, president of Grid Strategies.

PJM and MISO account for most projected charges

Grid Strategies estimated that data centers in PJM’s and the Midcontinent Independent System Operator’s (MISO’s) regions would account for approximately 82% of the projected $5.53 billion in annual charges.

The analysis assigned about $2.31 billion in annual charges to PJM and $2.25 billion to MISO. It projects 13.4 gigawatts of new data center capacity in PJM and 16.7 GW in MISO. PJM’s higher charges, despite its smaller projected pipeline, reflect the region’s higher transmission rates, Gramlich said.

Grid Strategies based its incremental transmission cost estimates largely on MISO data. The analysis includes 163 approved transmission projects representing approximately $11.4 billion in investment to connect 43.5 GW of large loads. Researchers calculated an average incremental cost per megawatt and applied it across the regions they studied.

Grid Strategies estimated the projected revenue could support nearly 10,000 miles of new 765-kilovolt transmission lines over 10 years. That construction would depend on when and where data centers connect to the grid.

The analysis excluded Texas’ ERCOT market, where FERC doesn’t traditionally regulate transmission service.

Grid connections likely to remain attractive

Higher transmission charges could make locations with available electrical capacity and predictable power-delivery timelines more attractive. Developers could also turn to behind-the-meter generation to reduce their reliance on utility-supplied electricity.

Gramlich said he doesn’t expect most data centers to abandon grid connections. Reliable power from an entirely off-grid system generally costs more and presents greater operational challenges, he said. He expects behind-the-meter generation to supplement utility service rather than replace it, potentially reducing the incremental transmission charges associated with a project.

The $55 billion estimate assumes new data centers take firm transmission service. Developers that operate entirely off grid wouldn’t generate those charges. Gramlich said that scenario is unlikely because data centers still derive substantial value from grid connections.